George Bourke Drive

Commercial Reclad, completed 2023

This project had extensive site retaining, siteworks and phased pours of 330m3 of concrete to form the new parking lot with all new kerbing. The main office reclad consisted of building a new entry canopy and recladding the building with colour steel.